The rain kept the guys from pouring cement on Friday so no new pics to post. They'll be ready to pour on Monday morning. I'll be out of touch for a while so won't be able to post any updates but hopefully my next one will show the completed pool. The current plan is:
Monday - Concrete
Tuesday - Removing forms and sealing concrete
Wednesday - Finishing touches and final pool hook-ups
Thursday - Pool cover installation and clean-up
The following week the landscapers, irrigation guys, and fence guys will do their thing. I'm told they will be able to finish everything in a week, which will be impressive considering there are several landscaping beds that will be made, over a hundred things to plant, a lot of sod to go down, many sprinklers to fix, and a yard drainage system to install. If they can all pull it off it'll be just in time for a pool party on the 6th! If they can't, oh well... close enough to break it anyway I guess.
No comments:
Post a Comment